Restoration work to begin at AquariumMonday, August 28, 2017
Work to repair hurricane damage at the Bermuda Aquarium, Museum and Zoo from the past few years is due to begin on September 5 and will last about a month.
BAMZ: Restoration Work On Property Foreshore
Monday, August 28, 2017
The Bermuda Aquarium, Museum and Zoo [BAMZ] have advised that work will soon begin to restore the property’s foreshore area on Tuesday, September 5 which has been damaged by hurricanes over the last few years.
BZS scholarships handed out
Wednesday, August 23, 2017
Akinyi Apopa and Amber Reid are the winners of the Bermuda Zoological Society’s Steinhoff Scholarship for 2017.
Aming stars as Shark Week hits screens
Wednesday, August 09, 2017
Choy Aming’s phone started ringing the moment Shark Week hit Canadian television last month.
Rescued turtle returns to the open sea
Tuesday, July 25, 2017
A loggerhead turtle rescued by divers has been returned to the sea after nine months of care.
About
GovernanceAbout Us
Newsletter
Latest News
Gift & Bookstore
Contact
General Inquiries
info@bzs.bm
Latest News
All the latest updates and news from the Bermuda Aquarium, Museum, and Zoo, one of Bermuda's leading visitor attractions!
By Simon Jones
Published Jan 15, 2015 at 8:00 am (Updated Jan 15, 2015 at 3:14 pm)
Click here to see an Aquarium update from Dr. Ian Walker, Principal Curator at th Bermuda Aquarium, Museum & Zoo.
Work on the aquarium’s new roof is over halfway complete and the project remains well on track, according to Dr Ian Walker.
The Curator of the Bermuda Aquarium, Museum and Zoo told The Royal Gazette he hoped the major construction work would be completed by March and the main hall would be open to the public again in April.
A Sunrise Construction crew member continues work on the roof structure improvements
at the Bermuda Aquarium Museum and Zoo (Photo by Akil Simmons)
A crew from Sunrise Construction continue work
on the roof structure improvements at the Bermuda
Aquarium Museum and Zoo (Photo by Akil Simmons)
Dr Walker admitted there had been a drop-off in visitors since Christmas, and suggested that it could be because many people mistakenly believed that the aquarium was closed.
“We are very much open,” he said. “The only part of the aquarium and zoo that is closed is the main hall that housed the majority of the fish tanks. These animals have been moved behind the scenes while the work continues.
“The Northrock tank is still open and we would urge people to visit as they usually would.”
Team effort: A crew from Sunrise Construction work on the roof structure improvements
at the Bermuda Aquarium, Museum and Zoo (Photo by Akil Simmons)
A crew from Sunrise Construction continue work on the roof structure improvements
at the Bermuda Aquarium Museum and Zoo (Photo by Akil Simmons)
The project, which began in October, has involved the complete demolition of the old roof and a series of new steel beams, which will form the frame of the new roof, have already been installed.
Just last week crews from Sunrise Construction began to put the corrugated roofing into place.
A crew from Sunrise Construction work in the main hall of
Bermuda Aquarium and Zoo (Photo by Akil Simmons)?
Construction workers tackle roof repairs at Bermuda Aquarium,
Museum and Zoo (Photo by Mark Tatem)?
Dr Walker said: “We are very happy with how the work has progressed.
“We are on schedule and the guys are working seven days a week to get the job done.
“There is still a lot of work to be done even after the roof is completed.
“We hope to be able to start working on the interior of the main hall in February to reinstate the tanks and start putting up new graphics.”